Our work in the media sector has continued with a slightly different slant lately. Over Christmas 2021, we were asked to provide adaption works to an existing lighting rig within a constrained shutdown window. Having successfully achieved this complex operation on time, we continued to support our client throughout 2022 with consultancy services consisting of specialist design advice and weekly inspections. The lighting rig is approximately 5,300 m3 at a height of 18 m from the ground with 6 nr emergency Hakki staircases.
We were asked to dismantle the entire rig, which provided additional challenges due to the time that it had been in place and the sequencing that we had to undertake to ensure the safety of the operatives at all times. The dismantle & demobilisation is now complete, providing our client with a clear structure for future activities.